During the third year of the project the following SP5 research activities were performed:

    • Commissioning of the facilities is achieved.

    • Calibration methodology has been released and discussed with icing community.

    • Instrumentation for calibration has been assessed.

    • Calibration of the facilities has started and is on-going.
    • Assessment of ice detectors developed in SP4 is on-going.
    • Test specimens for SP6 validation tests have been defined.

Despite some difficulties and delays, the majority of the SP5 objectives set for the third year of the project are about to be achieved.

In what follows the significant results of each WP of SP5 are presented.

WP51 : SP5 Coordination

WP53 : Technology ice crystal generation

WP54 : Calibration of test facilities

WP55 : Test campaigns

To view the progress performed within the firstsecond and fourth year of the project please follow the related links.